The fuel complex is now under technical retooling for further production of fuel elements for OAO ‘GNC NIIAR,’ Dimotrovgrad.

Building: 180

Staff: 45 workers.

 From June, 6 through June, 20 the project owner had a special committee examining the site. Right now paperwork is being prepared for 3 sites there (control, repair, and KR-01) for the State Commission. The commission visit is scheduled for June, 26.

Vents:  the smoke ventilation pipes are now being replaced on a par with the fireproofing system, progress is at 83%.

Low-voltage grids:  firealarm system is being installed as well as other internal alarm equipment, progress 75%.

. Cable passaged are currently being put in place for further feeder cable laying inside the main building.