The ‘Meschanskaya' - 'Krasnoselskaya' SS feeders.

Total length between the two is 10762 m. 10160 is done.  Cable laying – done across 18 sub-sites, total length is 60960 out of 64572.  In progress now is the installation of cable constructions (joints, passages, overpasses); progress by unit - 1st unit is 100%, 2nd unit is 95%, 3rd unit is also 95%.