Konakovsky SDPS. Accomplishment of the complex of works on developing of industrial control system of Konakovsky SDPS 6th power unit.
Electrical installation and commissioning of masout department, installation of equipment on indoor switchgears ZRU 35 kV, ZRU-110, main switchgear GRU-6 (replacement of cells).
HZhO-2 modernization, technical rearmament and overhaul of systems important for safety; works according to GAN and VPO instructions.
Installation, construction, commisioning works on replacement of AT-2 on substation of 330 kV Talashkino (with supply of equipment).
Expansion of outdoor switchgear ORU-110 kV — construction of indoor switchgear ZRU-6 kV on Smolensk HEPS-2 for connection of PNS No. 3 on 2 Verkhny Volok St.
Installation of relay protection of 220 kV and control cables.
Outdoor switchgear ORU 220 kV. Reconstruction of relay boards, installation of schemes of high-voltage switches heating.
Reconstruction of the boiler unit gas equipment No. 3 TP-87 on Ivanovo HEPS-3.
Installation of power supply system on object 15/155-3k (Teykovo, Ivanovo Region).
Installation works on the boiler room.
Reconstruction of remote control means of Ivanovo HEPS-1, HEPS-2, HEPS-3
HEPS-9. 1st stage of electrical installation works on GTE-65 input with generator of 65 MW and utilizer boiler with capacity of 90 tons of steam/hour.