Work of the Kurchatov branch, May 2013

17.06.2013

1. Kursk power plant.

Radioactive waste facility.

  • Electric equipment installation and cable laying.

Automated chemical control facility #3 and #4.

  • Setup of control lines, vales, control boards.

Spent-fuel storage.

  • Electric gear installation, cable laying, fire-retardant coating

New-fuel storage.

  • Electric equipment installation, cable laying.

3rd and 4th power units, bld. 914/2, 510/2, 061/2, 914/1.

  • Renovation of the lighting system according to the effective regulations.

2nd and 3rd power unit.

  • Smoke exhaust system.

330 kV outdoor switchgear.

  • Replacement of breakers.

2nd line, 3rd unit. Setup of a local computer network for the automated monitoring/control system.

  • Cable shafts, outlets, cable laying, wiring.

3rd unit. Replacement of 0,4 kV breakers.

  • Removal and installation of new actuators, aluminum busbars, wiring, terminators.

3rd unit. Software/hardware suite, monitoring system at the nuclear building, turbine block.

  • Cable laying, optical readings, installation of metalwork constructions.

Spent-fuel facility LAN.

  • Electric gear (installation), patchcords, control boards and outlets.

Replacement of equipment at 0,4 kV switchgear, bld. #54.

  • Cable laying, de- and pressurization of cable penetration units.

2. Novovoronezhskaya NPP, 5th unit.

5th unit, integrated switchgear.

  • Cable laying work.

5th unit. Boric acid concentration measurement.

  • Cable laying, boxes, containers, joints, shafts, etc.

3. Stoilensk ore mining and processing complex.

35/6 ‘Otvalnaya-1’ substation.

  • Setup of a condenser unit and a fire-alarm system.

Main stepdown substation-06. Dielectric oil storage.

  • Installation of complex electric gear.

4. Second launch area of the Nyaganskaya GRES.

Overpasses and support constructions for industrial pipelines.

  • Cable laying (power and control), passages.

Turbine block.

  • Installation of KRUZA P equipment, metalwork constructions for electric gear and local cable passages, cable laying. EC&I equipment (installation), installation of testing and welding systems. 