Projects of the Kurchatov branch, March 2012

02.04.2012
  1. Kursk NPP.
    • Renovation work at the 4th unit of the plant: cable coating (fire-retardant composition);
    • Steam compressor - 4th unit: cable laying;
    • Relay protection system: cable laying/wiring;
    • Renovation of fire fighting equipment: protective pipes, cable laying, fire fighting system;
    • lighting systems - removal and installation work: cable laying/wiring;
    • ISFSI: equipment installation, wiring, cable laying;
    • NPP simulator – renovation work: equipment installation, wiring, cable laying;
    • Command post: equipment installation, wiring, cable laying.
  2. Adler NPP.
    • Main building, unit 1:
      • lighting system for the turbine network, light beacons;
      • lighting system between sections B and V, level +18;  lighting system on the 2nd and 3rd staircases;
      • lighting system for the turbine area, level +2.2 and +5.0;
      • outlet network, installation/wiring; level +15.85;
      • roof beacons;
    • Main building, unit 2:
      • lighting system on the 1st and 4th staircases;
      • lighting system, levels +9.0; +15.85; +21.15;
    • 2nd unit - current distributors and busbar systems;
    • auxiliary equipment building at unit 2 (gas turbine section);
      • metalwork constructions;
      • outdoor/indoor grounding grid;
    • CAM systems: indoor grounding grid;
    • Secondary switchgear building (110 and 220 kV): protective beacons;
    • metalwork constructions at the overpasses;
    • Dry cooling tower: equipment installation, cable laying/wiring, lighting systems, indoor grounding grid, metalwork constructions;
    • A&LQ: metalwork constructions, grounding grid;
    • Units 1 & 2: cable laying/wiring.