Work of the Kostroma branch at the Nyagan GRES, December, 2010

Work of the Kostroma branch at the Nyagan GRES, December, 2010
25.01.2011

 

Work at the heating room and temporary-power-supply facilities (all under the PU-1-construction project) of the Nyagan GRES (420 mW capacity): 
Construction/installation of cable passageways at the BOP switchgear;
Work still underway at the temporary-supply power facilities of the boiler room, main building and pump station;
All relevant cable materials have been provided to temporarily power of the GRES fire-fighting facility;
Boxes, transformers (KRU-6kV, RU-0,4kV) at the BOP switchgear facility;
The main chimney has been equipped with a flash beacon;
EC&I work;
Cable work, liquid fuel equipment – work in the initial stage;
 

\\