Work done by the Kurchatovo branch in December, 2011

23.12.2011

 

At the Kursk NPP the branch did some work related to oscillographic testing, lighting system setup, fire safety equipment installation and other stuff – all at the 3rd and 4th units of the plant.   Some of the work also went on at the spent-fuel storage sites of the station.  Equipment replacement activities at SSG-330 kV (1st line) and SSG-750 kV (2nd line) of the Kursk NPP.

ECM also continues work at two power units of the Adler TPP (total capacity of the plant is 360 mW, 180 mW each), which includes installation jobs (auxiliary electrical equipment), cable laying and material provision – all within the framework of the “Adler TPP” project.

At the 5th unit of the Novovoronezhsk NPP we are now performing a number of post-reconstruction activities.
EMC is now also doing full-overhaul work at the Orlov TPP.

Detailed description:

  1. Kursk NPP:
    • 3rd power unit: partial replacement of the lighting system and some balancing equipment;
    • SSG-750 (2nd line):
      • Removal and installation of circuit breakers;
      • Oscillographic testing of the 4th power unit;
      • control cable laying/connection;
      • renovation work on the fire fighting equipment (3rd unit);
      • protective pipes, cable laying, installation of boxed switches;
    • Relay protection system of 4th unit:
      • coating the cables with fire-retarding substances;
      • 6 kV circuit breakers, 4th unit;
      • Defragmentation of 6 kV VEM breakers;
    • Unit control/monitor system, 4th unit: breakers, retainers, metalwork cable constructions;
    • Unit control/monitor system-7.8 (4th unit): cable laying, terminators, T-joints, valves, pipes, EC&I systems;
    • 4th unit itself:
      • fiber cable laying;
      • lighting system setup;
    • Spent fuel-storage site: power equipment installation, cable constructions, cable laying/connection works, lighting system setup.
  2. Adler TPP:
    • main building, No1:
      • outdoor grounding grid, relay protection systems, power lines,
      • secondary control wiring;
    • the SS supporting facility: outdoor grounding grid, the power transformer wiring, 0.4 kV busbar feed to the 2nd unit;
    • Control room: metalwork cable construction, lighting system, outdoor and indoor grounding grids;
    • the auxiliary equipment of the 2nd gas turbine (1st unit): cable laying/connection work;
    • outdoor grounding grid, lighting system, all sorts of sealing activities;
    • steam-turbine sites (2nd unit):
      • metalwork cable constructions;
      • metalwork cable through overpass constructions;
    • fan cooling tower: equipment installation, metalwork cable construction;
    • 2nd unit, main building: lighting system setup (+15.850), metalwork cable laying work;
    • 1st unit, third stairway: lightning system installation.

The Orlov TPP. Cable boxes (installation work) in the boiler room of power unit 2.