The Nyagan SDPS

Full range of activities regarding the provision of all necessary electric equipment, materials; installation of the EC&M equipment at power units 1, 2, 3, main building, auxiliary buildings, etc. 

The Kostroma branch is currently getting the following done:

  •  Fireproofing of cable passages and joints
  •  Installation of EC&M equipment
  •  Cable laying (0.4 kV, 6 kV)
  •  Control cable laying
  •  Lighting systems for the electrolysis rooms, gas materials store, fire station, hydrogen/argon ramps
  •  Installation of a 0,4 BOP switch gear, batteries, relay boards
  •  Installation of PMG equipment (permanent magnet generator)
  •  Terminal boxes for 6 kV cable
  •  Setup of a grounding grid
  •  Lighting system for the auxiliary buildings
  •  Secondary control wiring (6 kV)
  •  Setup of testing and welding power grids
  •  Installation of ‘KRUZA-P’ switchgears
  •  Installation of 6 and 20 kV current distributors
  •  Cable metalwork constructions, protective piping
  •  EC&M equipment (full range of activities)
  •  Installation of minor mechanic, control and electric equipment (control boards, boxes, switchboards, etc)
  •  Installation of the measuring equipment for the steam tourbine
  •  Control boxes for air inlets