Renovation of the industrial sewage system for OAO ‘GNC NIIAR' in Dimitrovgrad, Ylyanovsk region.

Staff: 25 workers.

Laboratory (adjunct to building #239):

 all doors installed, except the front one.  Completed work:  ventilation system is 98% in place, pipelines one the 1st and 2nd floor 90% completed, internal utilities – 63%, inside finishing work 95%, doors 60%, windows 90%.

Logistics roads behind the OAO ‘GNC NIIAR’ building:

 Stubs removed from the ground over a 700 meters out of 1482 way behind the building.  Temporary road is currently being set up – sand embankment in place, 200 by 6,5 meters. 

Water disposal and sewerage systems at site 1 is currently being set up.

 Current work: preparations for a B-5 water reuse system, a trench has been dug out (500 meters out of 780 target, pipes are now in place over a 150 m way, diameter 300 mm). Currently a foundation is prepared for a pump station there. 