The ‘Generalskaya’ substation, Rostov-on-Don.

 

Current work: bunding of the fence, reinforcement of the firewater tanks. All the concrete work is scheduled for June 26, volume 24 m3.  A water-well hole has been drilled (78 meters deep). A new trench has been prepared for a new pump building. 36 piles driven in for the substation control building,  26 other piles are now being installed for the indoor switchgear,  work is scheduled to be completed June, 21.  Starting from June, 22 we’ll be installing new piles for the auxiliary transformers. Work should be finished around June, 24. The ‘Rostovskaya’ – ‘Generalskaya’ SS merger is now pending a new contractor (3 potentials are being considered). 

 