Staff: 12 workers, including 10 wiremen.
General construction work involves:
Internal doors have been installed (53 total, 4 fireproofed) – out of 56 target. . Finishing work is now underway – both inside and out. Floors – almost completed. Hanging ceilings – 342 sq. m. out of 380 target.
Electric work:
Completed work: Internal grounding system – 1290 m out of 1310 target done, lighting system – 98% progress, heating system – all done. Currently cable joints and passages are being installed. Starting from June, 24 work will include the installation of a new lighting system.
Internal utility networks:
K-2 storm water drain - completed (minor details left).
Internal engineering network:
K-1 and K-2 storm drain – 98% competed, only testing remains to be done. Water conduit – 98% done.
Vents: Ventilation system is in place. Air conditioning – 98%.