SF6 switchgear at the Serovsk GRES, Serov.

Staff: 12 workers, including 10 wiremen.

General construction work involves:

 Internal doors have been installed (53 total, 4 fireproofed) – out of 56 target.  . Finishing work is now underway – both inside and out.  Floors – almost completed. Hanging ceilings – 342 sq. m. out of 380 target.

Electric work:

Completed work:  Internal grounding system – 1290 m out of 1310 target done, lighting system – 98% progress, heating system – all done.  Currently cable joints and passages are being installed.  Starting from June, 24 work will include the installation of a new lighting system.

Internal utility networks:

 K-2 storm water drain - completed (minor details left).

Internal engineering network:

 K-1 and K-2 storm drain – 98% competed, only testing remains to be done.  Water conduit – 98% done.

Vents:  Ventilation system is in place.  Air conditioning – 98%. 