The 'Krasnoselskaya' – TPP-23 feeders.

Stage 1 – micro-tunnel #1 (900 m) Statement of conformity signed.

Stage 2 – micro-tunnel #2 (1560 m) Work is completed, land improvement is underway.

Stage 3 – cable laying. The complete route is 11490m; 10554 is done.   Cable laying work at sub-site 21 is currently at 61560 m out of 68940. M6-M7 strip is now under ground construction, the trench is 50% completed.  In progress is cable pitting on the M7-M8 strip. Land improvement activities are being conducted across the entire way. 