The substation Krasnoselskaya is constructed on the territory of CAO of Moscow to the address: ul. Baumanskaya and ul. Olkhovskaya crossing. It is going to be a three-storey construction of 80х34,5 meters in size. Full complex of construction and electrical installation, commissioning works is performed on the object.
The substation was put into operation in 28.12.2010.
Construction of the 2nd launching complex is conducted: connection of 10200 meters long cable lines KL 220 kV from substation Krasnoselsky to HEPS-23
Customer: Energokompleks JSC
Beginning of construction: August, 2009.