List of projects by the Nizhni Novgorod branch, July-August 2012

22.08.2012
List of projects:

“Novogorkovskaya” TPP, renovation of WPP, Kstovo town.
  • Installation of EC&I pressure-gauge units.
  • Installation of EC&I equipment.
  • Cable laying (power and control cable).
  • Secondary control wiring.
“Serovskaya”GRES, Serov town. 370-tonn overhead crane (manufactured by “KONECRANES”) – installation/commissioning in unit 1. On the grounds: power units 9 and 10 – construction work, including a 420 MW CCGT).


“Centralnaya" substation (110 kV), Ulyanovsk.
Power equipment for an open switchgear at units 7 and 9 (110 kV).
110 kV busbar systems at units 7, 8, 9.


“Novaya” substation (110 kV), Penza.
  • Setup of a temporary power feed.
  • Removal of power equipment at a 110 kV open switchgear.
“Zhigulevskaya” hydro power plant, Zhigulevsk.
  • Removal of power equipment at the OSG of the 3rd turbine generator.
  • Installation of power equipment at the OSG of the third turbine generator.