Projects of the Kurchatov branch, September 2012

07.11.2012
1. Kurskaya NPP
  • 1st power unit: ORU-330 kV; replacement of some equipment
  • 3rd unit: TG5 and TG6 feed systems;
  • 3rd unit: main circulation pump (cable replacement); installation of SK boxes; cable laying work; metalwork constructions, valve installation.
  • 3rd unit of the diesel plant: EC&I equipment installation;
  • 3rd unit of SVO-3: removal of some SK boxes (26 units total); removal of some metalwork constructions (850 kilos total); removal of cable (95 km in all);
  • 3rd power unit: installation of terminals, breakers, amplifiers and other electric equipment
  • 3rd unit BSchU-O: equipment installation, control cable laying, etc;
  • 3rd power unit PTK: cable laying, metalwork constructions, equipment;
  • 4rd unit: cable laying, pipes, metalworks, sealing of some passes;
  • ISFSI: cable laying
  • Fortified command post: electric equipment (installation), lighting systems, cable laying
2. Some work is still underway at two power units of the Adlersaya TPS (180 MW each unit)


3. A number of power-related jobs have been completed at the “Bocharov Ruchey” substation (110 kV), involving power feeds and supply systems.

4. Novovoronezhskaya NPP. Cable laying, installation of some control/electric boxes and panels.
5. Stoilenski mining plant
6. GPP-05: power feeds (installation). Replacement of some 10kV breakers
7. HCS (heating control station) “Alexandrovka” – some work on the foundation; installation of 10 box units;
8. HCS “Otvalnaya” – general construction work; land planning; foundation trenches, lining, installation of foundation boxes. 