Kursk NPP

  • Outdoor switchgear (750 kV) – cable laying/wiring;
  • Installation of protective pipes, power cable laying, fire fighting system setup;
  • Unit 4: removal and installation of a new lighting system, cable laying/wiring;
  • ISFSI (spent-fuel storage): equipment installation, cable laying;
  • Command post: equipment installation, cable laying.

Adler TPP

  • A range of activities there (took place at two of the NPP power units): electrical equipment removal/installation, cable laying, auxiliary equipment setup, cable overpasses, lighting system setup, etc.