Projects of the Moscow corporate branch in March, 2011

06.04.2011

 

Full list of projects:

“Krasnoselskaya” substation. Customer – OAO “Energocomlpex”

  • security system;
  • Fire-safety system, installation;
  • security lighting system;
  • angular protection system.

 

TPP-20, an OAO “Mosenergo” branch.Customer – OAO “Mosenergo.”

Equipment replacement work (control board, 0.4 kV and cable network)

  • Cable work;
  • general construction activities;
  • Testing work;
  • reconnection to a new control board;

 

“Novo-Izmailovo” substation. Customer – OAO “Energocomplex”

  • ventilation system;
  • grounding grid;
  • metalwork constructions, rigid busbar systems at current-limiting reactor rooms;
  • lighting system setup;
  • isolating switches, 20 kV;
  • Installation of a T1 power transformer (TDCN-100000/220-U1);
  • Equipment installation work (relay protection system);
  • power cable work.

 

KUTES-40. Customer – Chernyshov MMP, primary contractor – OOO “Energoavia-MT”

  • power cable work.
  • CAD systems (GTU-1 and GTU-2), installation;

 

“Novo-Kuzminki” substation. Ordering party - OAO “ECM”

  • automated fire-safety system;
  • fire alarm system, installation;
  • Commissioning paperwork.

 

Southern power systems, an OAO “MOESK” branch. Customer – “YuES”

  • transformer substation (installation work); “Klenovo 1,” “Batybino 1,2.”
  • overhead/cable transmission lines;

 

TPP-9, an OAO “Mosenergo” branch.Customer – OAO “Mosenergo.”

Replacement of a 0.4 kV circuit board (No 5).

  • cordage works;
  • control-boards, 0.4 (installation);
  • cable work;

 

Cable gallery for 220 kV cable network running from the “Novo-Kuzminki” SS toward the “Tchagino” SS.

  • cable construction overhaul for further 220 kV cable installation;

 

Eastern power systems, a branch of MOESK. Ordering party – VES.

  • overall preparation work on the site;
  • Electrical equipment installation at GRU–10kv;