Projects of the Kurchatov branch in March, 2011

26.04.2011

 

Renovation work at the 5th PU of the Novovoronezh NPP

  • installation/removal of equipment – 54 units total, cable laying (21 km long); SUZ-6kV
  • Removal of SAE-2 equipment, room E115 (76 units);
  • Installation of KRU-0.4 (10 units), SPT (12 units), PMS-80 (10 units), removal of 6kV breakers (16 units). SAE-2 SNE VB;
  • Equipment removal work (4 units total); SAE-1 SNE VB;
  • Impulse lines (5 km), valves (193 units), T-joints (148 units), control-boards (59 units), joints (40), stoppers (40 units); TTK RO;
  • Penetration flanges (20 units), repair work; rooms E59, E60;
  • Various installation works (over 100 units), power cable laying (1,1 km), control cable (7.9 km), grounding grid (90 m total), cable circuits (1.5 km); control/protection systems;
  • Cable laying work at CPS-2, 11.2 km.
  • Equipment installation (18 units), fiberglass cable work (15.1 km)
  • Cable laying work at CAE-1, 2 km.
  • Cable removal (10.6 km), 156 removed connectors;
  • lighting system setup; lamps – 133 units, cable – 2.1 km long, sockets – 21 units, breakers – 32 units;

 

KurskNPP

  • 3rd power unit. Vibration-control system (TG-5, TG-6) – removal work;
  • Control cable;
  • 4th power unit. Automated integrity-control system – termination seal-off (570 units);
  • PSE at 3rd unitCirculating pumps – valve installation (64 units);
  • 3rd power unit. Oscillographic testing. Cable laying/connection work (2,1 km);
  • 2nd power unit. Replacement of the pump drives;
  • PSE at 3rd unit Renovation work; Cable laying/connection work (8 km);
  • Installation of dampers (10 units);
  • 3rd power unit. Smoke removal system installation. Equipment installation (6 units); cable laying (1.8 km);
  • Cable laying. Installation of boxes; ITSO (2nd line); (550 m);
  • 2nd line Renovation work at SMT-A busbar;
  • PSE at 3rd unit Device installation (28 units);
  • PSE at 3rd unit KAES. Boxes – 15 units, equipment – 19, wiring parts – 140 units total.
  • Hotel. Cable laying work (0.8 km).
  • The ECN building. Cable laying (VVG 3x2.5, 560 m), lighting system setup.
  • 3rd PU. Installation of a protective pipe system (935 m), cable laying (1900 m), VVG 4x4 (700 m), KVVG 4x1.5 (400 m), KVVG 14x1.5 (500m), KVVG 19x1.5 (500m);

 

Construction work at PGU-120mW, incl, reconstruction of SSG-110kV (TPP-6, Perm)

  • Metalwork constructions;
  • Main building:
    • Metalwork constructions;
    • lighting system setup;
    • electrical work at GTU-11, GTU-12 (equipment installation, power/control cable, secondary wiring);
  • Secondary switchgear building – final stage of the electrical work, commissioning.

 

Adler TPP

  • Exhaust-heat boiler room (PU 1) Metalwork constructions, grounding grid (0.6 km total)

Open-air gas-turbine plant equipped with a exhaust-heat boiler. Metalwork constructions.