Projects performed by the NN branch of ECM in June, 2011

Projects performed by the NN branch of ECM in June, 2011
01.07.2011

 

Detailed list:

  1. At OAO “Vyksynski metplant,” Vyksa.Plate mill construction works.
    • Control cable pinout;
    • Secondary wiring work in the spare-parts/equipment storage;
    • fire-safety system – wiring;
    • 0.4 kV cable laying
  2. “Soyuznaya” SS
    • Installation of KP SSG-110kV (30%) boxes;
    • Connection of the control cable network to the relevant power equipment (SSG-110kV, 20%);
    • Connection of the power cable network to the relevant power equipment (SSG-110kV, 20%);
    • Installation of RPS boards and remote control equipment (30%);
  3. At the “Provokzalnaya” substation:
    • Takedown and transportation activities (T-2 transformer, went from the SS to the main building, incl. unloading work);
    • foundation fortification work (T-2 transformer);
    • cordage and installation of the T-2 transformer;
    • base insulators, installation work;   
  4. At the “Yasnogorsk” substation:
    • Takedown and transportation of a T-1 transformer;
    • Renovation work on the oil receiver of the T-1 transformer;
    • Installation of the T-1 power transformer;
    • relevant grounding work;
    • relevant cable/wiring work.
  5. “Pokrov” SSInstallation of CSR
    • construction work;
    • site preparation for the transformer;

cable work (control and power);