Projects of the Kurchatov branch in July, 2011

27.07.2011

 

Renovation work on the 5th power unit of the Novovoronezh NPP
SKU RO – cable work (total length – 68 km), installation of BAE boxes (378 units);
TTK RO (room 406/1-2), KMK installation, boxes (173 units), pipe work (overall length – 95.5 km), cable termination (350 units).
TTK TO – cable takedown (30 km in all), equipment removal (38 units); EC&I parts (installation work, 208 units).
BSU – follow-up work on the boards, remote control devices (24 units total).
“URAN-B” system: fiberglass cable work (15 km), special grounding grid (100 boxes, 1200 m worth of cable); equipment installation – 7 units.
SAE for SNE VB; cable takedown (25 km), socket installation (6 kV, 82 units), socket installation (0.4 kV, 430 units)
SKU SOB-3 – cable laying work (3 km altogether);
SUZ-1, SUZ-2, terminators (11000 units in all), fiberglass cable work (wiring, connection)
Replacement of IVS M-60 systems; equipment installation (IRS) – 27 units;
lighting system setup;
room T301: 55 lamps installed;;
the reactive impedance room: 24 lamps;
room E-110: removal activities;
socket installation (6 kV, 0.4 kV) – all in room T301 (55 lamps in all).
Kursk NPP
integrity control system of the 2nd power unit coolant (ACOTT-2): cable work (both control and power cable);
integrity control system of the 4th power unit coolant (ACOTT-2);
metalwork constructions, cable laying, installation of control boxes, boards, monitor devices, detectors etc.;
automatic chemical processor system (1 line, AKhK-1), building 54;
installation of control boards, relevant cable work;
gas circuit at 4th unit (part of PSE-4);
takedown of EC&I boards, impulse lines, cable, metalwork constructions, SKU GK equipment; installation of metalwork frames for relevant equipment, metalwork cable constructions, re-wiring at RTZO and BEZ boxes;
condensate purification activities at 4th unit (part of PSE-4)
takedown of EC&I boards, impulse lines, cable, metalwork constructions, re-wiring @ RTZO sections;
cable replacement according to thermal resistance; PSE @ 2nd unit – power cable work (total – 11 km);
replacement of lighting groups, PSE 3rd unit – 15 units;
renovation work at 4th power unit, installation of a major steel pipe, incl. braces, support constructions, and relevant cable wiring;
PSE at 4th unit
replacement of VEM breakers (6 kV, 86 units); lamps – 74 units in all;
RPS system at 4th power unit (part of PSE-4);
installation and takedown of various control boards (31 units in all); cable removal, cable laying (overall 10 km);
ABP-1, ABP-2, ABP SAOR at 4th power unit (part of PSE-4);
installation/removal of equipment – 28 units total, cable laying;
SSG-330kV (1 line); isolating switches – 2 units installed, cable work. 
Adler TPP
SSG-110/220 kV – metalwork cable constructions, cable laying (both power & control cable), ventilation control system (installation, relevant wiring), coupling capacitors, 110 kV HF chokes;
main building: lighting system setup, indoor grounding grid (-1,20 level, axes 1-5, rooms 110, 111, 112, 113); lighting system setup/indoor grounding grid (+9.00, +15.85 level; axes 1-5, rooms 308, 309, 409, 410, 411, 412);
main building (A-G lines): metalwork cable constructions (boxes KKB 0.95/0.6, KKB 0.65/0.6, KKB 3PO 0.2/0.5) lines A-B, axes 1-4;
cable overpass running from the main building to the SSG 110/220 kV – cable work;
cable overpass from the main building to the auxiliary transformer 110/6 kV – cable work;
cable overpass running from the main building to the fire pump station – cable work;
auxiliary equipment building KU No1 – cable work.
Full overhaul of Orlov TPP
cable boxes in the engine room of PU 1 - installation work
 