1. Kursk NPP

  • 3rd power unit and spent fuel storage (HOYaT). Radiation control system (SRK) modernization.

T-joints, valves and detecting devices installation, installation of control cables.

  • 3rd power unit. Control member (RO). UKLU replacement.

Cable laying.

  •  3rd power unit. Operating lifespan extension. Normal and emergency power system.

Busbars replacement.

  •  4th power unit. Operating lifespan extension. UKLU replacement.

Sockets installation. Cable cores connection.

  • 4th power unit. Operating lifespan extension. Emergency power supply system (SAE).

Power cable laying.

  • 330 kV outdoor switchgear (ORU). 20 sets of RNDZ disconnectors replacement.

Power and control cable laying.

  • 330 kV outdoor switchgear (ORU). Disconnectors and voltage transformers replacement.

VT-3 (9 phase) replacement. Control cable laying.

2. Novovoronezh NPP-2

  •  Instrumentation and control equipment and automatic process control system equipment installation at the 10UKC reactor auxiliary building.

Cable laying, package terminations installation and cable cores connection, lamps installation.

3. Novovoronezh NPP 5th power unit

  • Special water treatment facility instrumentation and control system (SKU SVO) modernization in terms of operating panels and 5th power unit detector panels.

Cable laying, package terminations installation.

  • Cable laying for modernization of the energy accumulators electric motors instrumentation and control system, controlled from the local control panel of the 5th power unit.

Cable laying.

  • Control cable laying in some machinery for 117SN and 243SN assemblies of the special water treatment panel of the 5th power unit.

Cable laying, package terminations installation, cable cores connection.

4. Mikhailovsky GOK (mining and processing plant)

  • Pelletization block of the kilning machine No. 3 technological complex. Mixing and homogenization section.

Cable metalwork and equipment installation. Cable laying. Switchgear, cabinets, control blocks and transformers installation.

5. Novogorkovskaya HEPS

  • Complex of electrical works at the object: “Novogorkovskaya HEPS reconstruction with combined cycle gas turbine installation”.