Smolensk branch report in November 2014

04.12.2014

1. Rosenergoatom branch Smolensk NPP. Desnogorsk.

 

·         Reconstruction

o    Fire protection system modernization in the 2nd power unit. Cable penetration technical state and performance characteristics renewal.

o    Building and installation of wireless communications system in process management based on the TETRA wireless telecommunications standard.

o    Power supply scheme modernization for the consumers of the conditioning refrigerating station (HSK). Electrical installation works.

o    Installation of the system of notification and fire evacuation of personnel.

o    Seismic protection system installation at the 1st and 2nd power units

o    Electrolysis plant secondary circuits installation in the 2nd power unit.

·         Nuclear waste reprocessing complex (KP RAO).

o    Electrical installation works.

o    Instrumentation and controls stands installation.

o    Radiation monitoring system installation.

o    Loading bridges electrical equipment installation.

 

2. NIKIMT-Atomstroy JSC

 

·         Storage and management of spent nuclear fuel. Spent nuclear fuel storage (HOYaT). Reconstruction. Extension. Electrical installation works.

 

3.  KVADRA, JSC branch - Western Generation. Smolensk HEPS -2, Smolensk.

·         Electrical equipment repair at the electrical workshop and the workshop of thermal automatics and control (TAI) of Smolensk HEPS-2.

·         Breaker back-up devices (UROV) installation at the 110 kV outdoor switchgear of the Smolensk HEPS -2, KVADRA, JSC branch - Western Generation.

 

4. IDGC Center, JSC branch – Smolenskenergo.

 

·         Cable lines repair in Smolensk.

 

5. Dorojnik, LLC, Bryansk.

 

·         Fiber-optic communication lines installation in the telephone conduit, in the house distributing systems and residential houses low-voltage lines, optical distribution frames and terminal boxes installation (Bryansk, Bejitsky and Sovetsky districts).

 

Works planned for December 2014

1. Rosenergoatom branch Smolensk NPP. Desnogorsk.

·         Reconstruction

o    Power supply scheme modernization for the consumers of the conditioning refrigerating station (HSK). Electrical installation works.

o    Fire protection system modernization in the 2nd power unit. Cable penetration technical state and performance characteristics renewal.

o    Building and installation of wireless communications system in process management based on the TETRA wireless telecommunications standard.

o    Refueling machine training stand valves electric drives replacement.

o    Electrolysis plant modernization.

o    Radiation control stations replacement at the 1st security desk of administrative building.

·         Nuclear waste reprocessing complex (KP RAO). Electrical installation works.

 

2. NIKIMT-Atomstroy JSC

 

·         Storage and management of spent nuclear fuel. Spent nuclear fuel storage (HOYaT). Reconstruction. Extension. Electrical installation works.

 

3.  KVADRA, JSC branch - Western Generation. Smolensk HEPS -2, Smolensk.

 

·         Replacement of the oil circuit breaker for the SF6 circuit breaker at the 110 kV outdoor switchgear of the Smolensk HEPS-2.

 

4. IDGC Center, JSC branch – Smolenskenergo.

 

·         Cable lines repair in Smolensk.

 

7. Dorojnik, LLC, Bryansk.

 

·         Fiber-optic communication lines installation in the telephone conduit, in the house distributing systems and residential houses low-voltage lines, optical distribution frames and terminal boxes installation (Bryansk, Bejitsky and Sovetsky districts).