Smolensk branch report in October 2014

28.10.2014

1. Rosenergoatom branch Smolensk NPP. Desnogorsk.

  •          Reconstruction

o    Installation of the system of notification and fire evacuation of personnel of the 3rd power unit.

o    Fire protection system modernization in the 2nd power unit. Cable penetration technical state and performance characteristics renewal.

o    Building and installation of wireless communications system in process management based on the TETRA wireless telecommunications standard at Smolensk NPP.

o    Power supply scheme modernization for the consumers of the conditioning refrigerating station (HSK). Electrical installation works.

o    Seismic protection system installation at the 1st and 2nd power units

  •        Nuclear waste reprocessing complex (KP RAO).

o    Electrical installation works.

o    Instrumentation and controls stands installation.

o    Radiation monitoring system installation.

o    Loading bridges electrical equipment installation.

2. NIKIMT-Atomstroy JSC

  •        Storage and management of spent nuclear fuel. Spent nuclear fuel storage (HOYaT). Reconstruction. Extension. Electrical installation works.

3.  KVADRA, JSC branch - Western Generation. Smolensk HEPS -2, Smolensk.

  •          Electrical equipment repair at the electrical workshop and the workshop of thermal automatics and control (TAI) of Smolensk HEPS-2.
  •          Breaker back-up devices (UROV) installation at the 110 kW outdoor switchgear of Smolensk HEPS -2, KVADRA, JSC branch - Western Generation.

4. IDGC Center, JSC branch – Smolenskenergo.

  •          Cable lines repair in Smolensk.

5. Dorojnik, LLC, Bryansk.

  •          Fiber-optic communication lines installation in the telephone conduit, in the house distributing systems and residential houses low-voltage lines, optical distribution frames and terminal boxes installation (Bryansk, Bejitsky and Sovetsky districts).

Works planned for November 2014

1. Rosenergoatom branch Smolensk NPP. Desnogorsk.

  •          Reconstruction

o    Installation of the system of notification and fire evacuation of personnel of the 3rd power unit. Pre-commissioning works.

o    Seismic protection system installation at the 2nd power units

o    Power supply scheme modernization for the consumers of the conditioning refrigerating station (HSK). Electrical installation works.

o    Fire protection system modernization in the 2nd power unit. Cable penetration technical state and performance characteristics renewal.

o    Building and installation of wireless communications system in process management based on the TETRA wireless telecommunications standard.

o    Electrolysis plant modernization.

o    Radiation control stations replacement at the 1st security desk of administrative building.

  •        Nuclear waste reprocessing complex (KP RAO). Electrical installation works.

2. NIKIMT-Atomstroy JSC

  •          Storage and management of spent nuclear fuel. Spent nuclear fuel storage (HOYaT). Reconstruction. Extension. Electrical installation works.

3.  KVADRA, JSC branch - Western Generation. Smolensk HEPS -2, Smolensk.

  •         Electrical equipment repair at the electrical workshop and the workshop of thermal automatics and control (TAI) of Smolensk HEPS-2.

4. IDGC Center, JSC branch – Smolenskenergo.

  •          Cable lines repair in Smolensk.

7. Dorojnik, LLC, Bryansk.

  •      Fiber-optic communication lines installation in the telephone conduit, in the house distributing systems and residential houses low-voltage lines, optical distribution frames and terminal boxes installation (Bryansk, Bejitsky and Sovetsky districts).