+7 (495) 272-0871
in 5 cities of Russia
№
Customer/Object
Work done
1
Novovoronezh NPP
220 kV substation Novaya
Precast ferroconcrete constructions installation
Ferroconcrete foundation works
500 kV outdoor switchgear
Metalwork installation
Bay support stands installation
Electrical equipment grounding installation
Automated personal dosimetry monitoring system (APDMS)
Finishing works
Heating, water-supply and sewerage systems installation
2
Novovoronezh NPP (under construction)
10 kV plant switchgear building
Electrical equipment installation
Fire house facilities complex
Equipment installation
Building for 0,4 kV auxiliary switchgear modular block
Modular building blocks installation
Serov SDPS
Chemical water purification building
Cable installation
6 kV cubicle switchgear
Subcommutation equipment installation
Power cable installation
Main building
Lighting installation
Cable metalwork installation
Cable laying
Subcommutation cable installation
Circulating pump station
Diesel fuel pump station
Crane installation
Transformer yard №1
Flood prevention
Back to the list