Works performed by Kurchatov branch in August 2014

02.09.2014

1. Kursk nuclear power plant

  • 3rd power unit and wasted nuclear power storage (HOYAT). Modernization of radiation control system (SRK).
    • Installation of tees, valves, detecting devices, installation and dismantle of cable.
  • 3rd power unit. Extension of operation term. Ventilation and air conditioning system.
    • Installation of equipment, cable laying.
  • 3rd power unit.  Extension of operation term.  BShchU-N.
    • Dismantle of equipment.
  • Equipping of the rooms of the 4th power unit with automatic installations of fire extinguishing and fire alarm system.
    • Installation of metalworks, laying of a control cable.
  • Modernization of outdoor switchgear (ORU) 750 kV of the 2nd line of Kursk NPP.
    • Replacement of a switch 5 IV-2 (3 phases). Replacement of disconnectors.
  • Outdoor switchgear (ORU) of 330 kV. Replacement of switches and transformers.
    • Dismantle, cable installation.
  • Construction and installation works on the local computer network of the system of the account and control of nuclear materials.
    • Installation of equipment.
  • Complex of processing of liquid radioactive waste (KP ZhRO) production building
    • Installation of ceiling illumination of the room 501.

2. Novovoronezh nuclear power plant-2

  • Installation of instrumentation and control. Installation of equipment of industrial control system on object: "The reactor auxiliary building 10UKC" of Novovoronezh NPP-2. 
    • Laying of a cable, installation of cable metalworks.

3. Novovoronezh NPP. 5th power unit.

  • Transfer of cable routes TA 13, 14.
    • Installation and dismantle of cable. Installation of metalworks

4. Mikhailovsky GOK

  • Building of pelletization of technological complex of the kilning machine No. 3
    • Installation of cable metalworks and equipment.

5. Novogor’kovskaya HEPS

  • Cable economy.  Main cable routes.
    • Cable laying, installation of cable metalworks.