Новости

Works performed by Smolensk branch in March 2014

24.03.2014

1. Rosenergoatom Concern JSC branch - Smolensk nuclear power plant. Desnogorsk. Reconstruction.
  • Reconstruction.
    • Modernization of special systems of 2nd power unit.
    • Installation and construction works on introduction of complex system of management and safety (KSKUZ ). USB-T, SKALA.
  • Installation of system of notification and stuff evacuation control, ABK.
  • Installation of LED lighting system in rooms of the main building and external constructions of Smolensk NPP.
  • Nuclear waste reprocessing complex (KP RAO). Launching complex. Special building. Electric installation work.
  • Modernization of electric equipment of the bridge crane mounted on wasted nuclear power storage (HOYaT).

2. NIKIMT-Atomstroy JSC.

  • Building on of wasted nuclear power storage (HOYaT). Reconstruction. Electrical installation work.

3. KVADRA, JSC, branch of Western Generation. Smolensk HEPS -2, Smolensk.

  • Repair of equipment of electrical workshop and workshop of thermal automatics and control (TAI) of Smolensk HEPS-2.4 .

4. IDGC of Centre JSC branch – Smolenskenergo.

  • Reconstruction of substation PS of 220 kV Vostok.
  • Installation and construction works on object "The distribution center combined with transformer substation TP (RTP-6/0,4 kV) to the address: Smolensk, per. Zapolny for needs of IDGC of Centre JSC branch – Smolenskenergo"

5. Energostroymontazh JSC.

  • Reconstruction of the main street with regulable traffic Normandy-Neman in Smolensk.

Planned works on objects in April, 2014.

1. Rosenergoatom Concern JSC branch - Smolensk nuclear power plant. Desnogorsk. Reconstruction.

  • Reconstruction.
    • Modernization of special systems of 2nd power unit.
  • Installation and construction works on introduction of complex system of management and safety (KSKUZ ). USB-T, SKALA.
  • Installation of LED lighting system in rooms of the main building and external constructions of Smolensk NPP.
  • Nuclear waste reprocessing complex (KP RAO). Launching complex. Special building. Electric installation work.
  • Modernization of electric equipment of the bridge crane mounted on wasted nuclear power storage (HOYaT)

2. NIKIMT-Atomstroy JSC.

  • Building on of wasted nuclear power storage (HOYaT). Electrical installation work.

3. KVADRA, JSC, branch of Western Generation. Smolensk HEPS -2, Smolensk.

  • Installation of the breaker back-up devices (UROV) of outdoor switchgear 110 kV of Smolensk HEPS -2.
  • Repair of electrical equipment of electrical workshop and workshop of thermal automatics and control (TAI) of Smolensk HEPS-2.

4. IDGC of Centre JSC branch - Smolenskenergo.

  • Installation and construction works on object "The distribution center combined with transformer substation TP (RTP-6/0,4 kV) to the address: Smolensk, per. Zapolny for needs of IDGC of Centre JSC branch - Smolenskenergo.
  • Reconstruction of substation Vostok.



More photo

Back to the list