Project works in February, 2014

21.02.2014
Project documentation on objects Kursk HEPS-1, Bytplast plant and Moscow Oil Refinery Gazpromneft-MNPZ JSC is being prepared. Implementation of project works proceeds. 
Construction design supervision is exercised on the following objects: substation of 220/10 kV Generalskaya, substation of 220/10 kV Kruglikovskaya, substation Tushino, overhead line VL-220 Generalskaya-Rostovskaya. 
A number of project works on object of Gazpromneft-MNPZ JSC is completed.