Works performed by Smolensk branch in December, 2013

24.12.2013

1. Rosenergoatom Concern JSC branch Smolensk nuclear power plant. Desnogorsk.

Reconstruction:

  • Modernization of 2nd power unit’s special systems. Construction and installation works on introduction of complex system of management and safety (KSKUZ). USB-T, SKALA.
  • Extension of 2nd power unit’s operation term.
  • Nuclear waste reprocessing complex (KP RAO). Launching complex. Special building.

2. NIKIMT-Atomstroy JSC.

  • Building on of wasted nuclear power storage (HOYaT). Reconstruction.

3. IDGC of Centre JSC branch - Smolenskenergo.

  • Reconstruction of distribution center RP-7 in Smolensk.
  • Reconstruction of substation of 220 kV Vostok.
  • Construction of cable lines KL-6 kV of distribution center RP-21-TP Horse racing school for technological connection of power accepting devices of horse-racing school to the address: Smolensk, settlement of Odintsovo.
  • Energo promstroy resurs

4. JSC Energostroymontazh.

  • Reconstruction of the main street of city value with adjustable movement Normandy-Neman in Smolensk.

5. JSC Monolitos.

  • Installation of support for a contact network of the tram line in Smolensk
  • Planned works on objects in January, 2014.

1. Rosenergoatom Concern branch of JSC Smolensk nuclear power plant. Desnogorsk.

Reconstruction:

  • Modernization of 2nd power unit’s special systems. Installation and construction works on KSKUZ introduction. USB-T, SKALA
  • Extension of term of operation 2 power units.

Nuclear waste reprocessing complex (KP RAO) Smolensk NPP.

2. JSC NIKIMT-Atomstroy.

  • Attach HOYaT. Electric installation work.

3. JSC KVADRA of Western Generation Branch. Software "Smolensk CHPP-2" Smolensk.

  • Installation of the devices of reservation of failures of switches (DRFS) to the outdoor switchgear ORU of 110 kV of software "Smolensk CHPP-2" Kvadra branch of JSC - "The western generation".

4. IDGC of Centre branch of JSC - "Smolenskenergo".

  • Installation and construction works on object "The distributive point combined with TP (RTP-6/0,4kv) to the address: Smolensk, Zapolny Lane for needs of JSC IDGC of Centre (Smolenskenergo branch).
  • PS "East" reconstruction.