+7 (495) 921-0871
in 5 cities of Russia
Staff: 52 workers, including 36 wiremen.
General construction work involves: Installation and setup of external utility networks (sewage – 99% completed, fire main – 99 % completed), except the B-1 network. In all, the utility network is now 98 % done. Installation of a hanging ceiling on the 3rd floor – 95% completed. The front is all done except the drain system. 6 kV cable overpass is in place. Current work now also involves land improvement activities.
Electric work: In progress now is the installation of cable constructions (joints, passages, overpasses); progress by unit - 1st unit is 100%, 2nd unit is 95%, 3rd unit is also 95%. Secondary control wiring is now being setup, heating system is 90% completed. Cable laying work is underway, current area is 23 sq. km out of 47. Major testing activities are also going on around the site.
Vents: Air ducts/pipes have most been installed, progress by floor: 1st – 99%, 2nd – 99%, 3rd – 95%.