Foundation bearers are currently installed, 17 out of 18 are in place. Completed work: Installation of girders around the perimeter - almost completed.
The engineering buliding
Current work: work is now on the perimeter foundation for further installation of bearers – progress is now at over 50% completed.
The waste storage:
Ground work is now underway, 130m3 has been removed from the main trench. Current work involves: Removal of the concrete foundation mattress around the trench perimeter, 20m3 has been taken out (36 total), the mattress is also being widened across the perimeter.