Новости

ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016

ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016
08.12.2016

1.    The development of design and estimate documentation for the project: "110/6/6 kV onsite and off-site power supply of 110 kV network for the site of serial production of JSC" PCU" is completed; address: Tula, st. Scheglovskaya abatis, 31 ".

2.       Works on the design of the facility of JSC "FOSAGRO Cherepovets":
· "AO" FOSAGRO Cherepovets "Phosphate Complex are completed. Fire Alarm Connection BKTP 17-3 to PD. "
· "Reconstruction of working and emergency lighting network of outdoor technological installations in the area of ammonia loading of JSC "FOSAGRO Cherepovets" "

3.       The works on the project: "JSC" FOSAGRO Cherepovets " are continued. Removal of power and control cables from the No-Go cable channel 301E body shop for the production of ammonia in the air №1 cable racks. "

4.       Works on the facilities of PJSC "Mosenergo" are continued:
· Development of working documentation on the project: "Connection of the data center to the power supply system" on CHP-12 branch of PJSC "Mosenergo" ".
· Development of working documentation on the project: "Connection of the data center to the power supply system" on the TPP-9 branch of PJSC "Mosenergo" ".

5.       The development of the documentation on the project: "Replacement of 35 kV equipment GLP-intake" for the needs of OJSC "Slavneft-Yaroslavl Refinery", Yaroslavl is continued.

6.       The development of working documentation on the project: "Upgrade of 110 kV outdoor switchgear including the replacement of equipment Yushkozerskaya HPP Cascade of Kema HPP of branch" Karelsky "of JSC" TGC-1 " " is on a final stage.

7.       The development of working document on a complex works on the project: "Extension of the operation unit №3 of Smolensk NPP" is continued.



More photo

ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016 ECM-Engineering: a report on the range of works performed by Electrotechnical department in November 2016

Back to the list